Print PDF
USPTO Fee Increases
October 2, 2020
USPTO Fee Increases
On October 2, 2020, certain fees charged by the USPTO will be increased. The USPTO indicates that these fee increases are necessary to keep pace with increasing costs and to provide for continued operations.
We recommend completing possible transactions with the USPTO before October 2, 2020 to avoid the cost increases.
Pre-examination Fees | |||
Large Entity | Small Entity | Micro Entity | |
Filing | $300 -> $320 | $150 -> $160 | $75 -> $80 |
Search | $660 -> $700 | $330 -> $350 | $165 -> $175 |
Examination | $760 -> $800 | $380 -> $400 | $190 -> $200 |
Total | $1720 -> $1820 | $860 -> $910 | $430 -> $455 |
Prosecution Fees | |||
Large Entity | Small Entity | Micro Entity | |
One-month Extension of Time | $200 -> $220 | $100 -> $110 | $50 -> $55 |
Two-month Extension of Time | $600 -> $640 | $300 -> $320 | $150 -> $160 |
Three-month Extension of Time | $1400 -> $1480 | $700 -> $740 | $350 -> $370 |
Four-month Extension of Time | $2200 -> $2320 | $1100 -> $1160 | $550 -> $580 |
Five-month Extension of Time | $3000 -> $3160 | $1500 -> $1580 | $750 -> $790 |
First RCE | $1300 -> $1360 | $650 -> $680 | $325 -> $340 |
Second and subsequent RCE | $1900 -> $2000 | $950 -> $1000 | $475 -> $500 |
Some other fees, such as prioritized examination (Track One) are going up as well. | |||
Large Entity | Small Entity | Micro Entity | |
Prioritized Examination | $4000 -> $4200 | $2000 -> $2100 | $1000 -> $1050 |
Request for expedited design examination | $900 -> $1600 | $450 -> $800 | $225 -> $400 |
Ex Parte Appeal Fees | |||
Large Entity | Small Entity | Micro Entity | |
Notice of Appeal | $800 -> $840 | $400 -> $420 | $200 -> $210 |
Request for Oral Hearing | $1300 -> $1360 | $650 -> $680 | $325 -> $340 |
Forwarding Appeal to the Board | $2240 -> $2360 | $1120 -> $1180 | $560 -> $590 |
Issuance & Post-Issuance Fees | |||
Issue fees for utility patents increase by 20%, while the first maintenance fee increases by 25% and late fees increase by more than 200%: | |||
Large Entity | Small Entity | Micro Entity | |
Utility Issue Fee | $1000 -> $1200 | $500 -> $600 | $250 -> $300 |
First maintenance fee (3.5 years) | $1600 -> $2000 | $800 -> $1000 | $400 -> $500 |
Second maintenance fee (3.5 years) | $3600 -> $3760 | $1800 -> $1880 | $900 -> $940 |
Third maintenance fee (3.5 years) | $7400 -> $7700 | $3700 -> $3850 | $1850 -> $1925 |
Surcharge for late payment of maintenance fee | $160 -> $500 | $80 -> $250 | $40 -> 125 |
Certificate of Correction | $150 -> $160 |